The Confederate States
|
| Appropriation for Engineer Service |
| To A. A. Traylor |
| |
| Date |
Designation |
Application |
Cost |
| Dollars |
Cts |
|
1863 |
|
|
|
|
|
Sept. 4 |
For hire of Slave Carpenters during the months
of July and August 1863, viz. |
Construction Appomattox Bridge on charge of
Confederate Track |
|
|
| |
Joe 18 days at $3.50 per day |
|
63 |
00 |
| |
Jesse 18
" "
" "
" |
|
63 |
00 |
| |
Henry 14 "
"
" "
" |
|
49 |
00 |
| |
Nathan 15 "
"
" "
" |
|
52 |
50 |
| |
|
|
|
|
| |
|
|
$227 |
50 |
|
| |
| I certify that the above account is
correct and just. |
| Chas. H. Dimmock |
| Capt Engrs |
| |
| Received at Petersburg Va. this 4th day of
September 1863 from Chas. H. Dimmock, Capt Engrs the sum of two
hundred & twenty seven 50/100 dollars in full of the above
account. |
| A. A. Taylor |